FACTORY & EQUIPMENT
Plant 2
The assembly hub for mass production & modification
✓ Completed April 2023 🏭 Site 10,015㎡ · SAS-dedicated
Plant 2, completed in April 2023, is JIWON M-TECH’s dedicated assembly hub. Mass-production assembly of HSC crawler-crane lower frames and assembly of Volvo excavator modifications are carried out mainly here.
📍 73, Bonsan-ro, Jinyeong-eup, Gimhae-si, Gyeongnam, Korea
Role as Assembly Hub
HSC Lower Frame Mass Production
We mass-produce and reliably supply crawler-crane lower frames and undercarriage parts for HSC Cranes.
View business →Volvo Excavator Modification
As a Volvo Construction Equipment SAS partner, we assemble and complete modification products including cabin, boom & arm and specialized equipment.
View business →Location
Facility Information
| Equipment | Specification | Remarks |
|---|---|---|
| Shop A | 20 × 69.3 × 12 m | Welding & SAS assembly |
| Shop B | 20 × 57.3 × 12 m | SAS assembly only |
| Overhead cranes | 20+5t×2, 10t×3 | Height 9 m |
| Wall-travelling cranes | 2.8t × 4 | Height 5.7 m |
| Paint shop | 8 × 14 × 12 m | |
| Welding robot system | 6+2 Axis · Payload 1.5t · 700A (Lincoln) | ×2 |